Construction on Highway 34

RE: PROJECT START-UP/MOBILIZATION
MTO CONTRACT NO. 2020-4081
HIGHWAY 34

Please be advised that Coco Paving will soon begin construction on Highway 34 for MTO Contract No. 2020-4081. The scope of work for this contract includes the widening of Highway 34 to accommodate the addition of a continuous two-way left-turn lane as well as dedicated left turn lanes at Perreault Street. Work includes; road widening, concrete work, ditching, culvert replacement, private entrance reconstruction and paving.

Contract Limits as follows:

  • Highway 34, from 160 m South of Perreault St. to 290 m North of Perrault St.

Construction Timeline:

  • The construction and implementation of traffic control measures are scheduled to start October 1, 2020 and continue until work completion December 4, 2020.

More details in attachment.

Attachments